SIENA PARK RESIDENCES - CONSTRUCTION UPDATES

March 12, 2012

Auburn Building- Structural works of Auburn Building are 100% completed

Cerise building- Sub structural works of Cerise building 100% completed

Citrine Building- Structural works of Citrine Building is 95% completed

Clubhouse 100% completed

Crimson building- On-going Sub Structure works of Crimson building

Indigo building- On-going structural works of Indigo building makes 3rd level

Lavender building- On-going clearing for Lavender building

Lilac Building- On-Going structural finishing of Lilac Building now at 70%

Magenta Building- On-going structural finishing of Magenta building now at 75%

Olive building- On-going Sub Structural works of Olive building is 100% completed

Peach building- On-going clearing for Peach building

Plum building- On-going structure works of Plum building

Pool Area and Pool Deck almost 100% completed

  


February 17, 2012
Auburn Building is 100% completed.

CERISE BUILDING Structural works of Cerise Building is now at 2nd level.

CRIMSON BUILDING Structural works of Crimson Building is now at lower ground level.
Citrine Building is 95% completed.

Clubhouse is 100% completed.

INDIGO BUILDING Structural works of Indigo building is now at 2nd level.
Lilac Building is 60% completed.

Magenta Building is 70% completed.

OLIVE BUILDING Structural works of Olive Building is now at lower ground level.
PLUM BUILDING Structural works of Plum Building is now at lower ground level.
Pool Area and Pool Deck is 95% completed.




January 13, 2012
Auburn
Cerise
Citrine
Crimson
Indigo
Lilac
Magenta
Olive
Plum
Clubhouse




October 17, 2011
Auburn Building
Cerise Building

Citrine Building

Clubhouse
Indigo Building

Lilac Building

Magenta Building
Olive Building


FEATURED NEWLY LAUNCHED PROJECT: BRIO TOWER in MAKATI!

Brio Tower Building Facade

Brio Tower Building Facade

DMCI Homes’ Brio Tower is strategically situated on a very prime location, near EDSA at the back of Pet Plans Building in Barangay Guadalupe Viejo in the city of Makati. Makati is known for its developed business district making it one of Asia's important financial, commercial and economic centers. Ideally located within Makati, Brio Tower will provide its residents the luxury of time and convenience as it is just a few minutes’ drive to Makati CBD, Rockwell Center, Bonifacio Global City, Ortigas and Greenhills. Read more>>>

Call our hotline no. (632) 369.9961 or text +63.917.838.7363 for reservation.

GRAB OUR PROMO AND OWN A UNIT NOW WITH OUR READY FOR OCCUPANCY PROPERTIES!

Siena Park Residences - Bicutan, P'que City

10% payable in 6 months (MOVE IN) and 90% balance through Bank Financing.


Arista Place - Sto. Nino, Paranaque City

10% Downpayment Payable in 6 months (MOVE IN) and 90% balance through Bank Financing.


Tivoli Garden - Mandaluyong City

10% payable in 8 months (MOVE IN) and 90% balance through Bank Financing.


La Verti Residences - Taft Avenue, Pasay City

20% CASH Downpayment (MOVE IN) and 80% balance through In-house or Bank Financing.


Illumina Residences - Sta. Mesa, Manila

10% payable in 8 months (MOVE IN) and 90% balance through Bank Financing.


Flair Towers - Reliance St., Mandaluyong City

20% CASH Downpayment (MOVE IN) and 80% balance through In-house or Bank Financing.


Royal Palm Residences - Acacia Estates, Taguig

10% payable in 8 months (MOVE IN) and 90% balance through Bank Financing.


Cedar Crest - Acacia Estates, Taguig City

10% CASH Downpayment (MOVE IN) and 90% balance through Bank Financing.


BEST TO INVEST WITH OUR PRE-SELLING PROPERTIES AT A REASONABLE PRICE AND RESORT-INSPIRED COMMUNITIES

Asteria Residences - Sucat, Paranaque

Price Range: Php2.53Mn - Php5.06Mn

2 and 3 Bedroom Units

Turnover Dates: April & July 2017


Torre de Manila, Taft Ave., Manila

Price Range: Php2.59Mn - Php6.15Mn

1BR, 2BR & 3BR Units

Turnover Date: November 2017

Sorrel Residences - Sampaloc, Manila

Price Range: Php1.92Mn - Php5.51Mn

Studio, 1BR, 2BR & 3BR

Turnover Date: January 2015

One Castilla Place - New Manila, QC

Price Range: Php2.53Mn - Php6.30Mn

1BR, 2BR & 3BR Units

Turnover Date: January 2016

Lumiere Residences - Shaw Blvd., Pasig

Price Range: Php2.09Mn - Php6.33Mn

Studio, 2BR & 3BR Units

Turnover Dates: Oct 2018 & June 2019


Sheridan Towers - Sheridan St., Pasig

Price Range: Php2.10Mn - Php4.54Mn

Studio, 1BR & 2BR Units

Turnover Date: November 2018

Viera Residences - Sct.Tuason, QC

Price Range: Php2.06Mn - Php4.58Mn

Studio, 1BR & 2BR Units

Turnover Date: March 2018

Zinnia Towers - EDSA Munoz, QC

Price Range: Php1.77Mn - Php6.80Mn

Studio, 1BR, 2BR & 3BR

Turnover Dates: May 2016 & Dec2017